07.01.2013 An extra grant of nearly PLN 100 million awarded for the construction of the LNG Terminal
The amount of the Operational Programme - Infrastructure and Environment (OPI&E) grant for the construction of the LNG terminal in Świnoujście has been significantly increased. The maximum sum of the subsidy was increased from...[more]
20.12.2012 LNG tank’s roof concreting operation has been started
On December 20th 2012, an extremely difficult and complicated operation of concreting the first tank’s roof has been started at the construction site of Swinoujscie liquefied natural gas (LNG) receiving terminal. Covering the...[more]
20.12.2012 Video footage from Świnoujście LNG terminal construction
This is our great pleasure to present three films made during the construction of the LNG Terminal in Świnoujście.
The films depict the complicated operation of tank’s roof air raising, construction of the breakwater in the...[more]
14.12.2012 Market Screening procedure has been extended until 11th January 2013
To meet the expectations of the prospective clients, due to significant interest in the market research procedure (so-called Market Screening) to assess the demand for the technical expansion of the terminal and the provision of...[more]
03.12.2012 Polskie LNG together with the EPC Contractor for the LNG Terminal providing assistance to the City Hospital and Fire & Rescue Service of Świnoujście
Polskie LNG Company together with the Saipem – Techint – PBG Consortium – the EPC Contractor for LNG Terminal in Świnoujście made donations for the City Hospital and Fire & Rescue Services of Świnoujście under ‘Social Civic...[more]
20.11.2012 Polskie LNG: Świnoujście LNG Terminal’s expansion aims to meet the market demand
Polskie LNG Company, established to construct and operate the liquefied natural gas (LNG) terminal in Świnoujście (Poland), on November 20th, 2012 launched a market research procedure (so-called Market Screening) to assess the...[more]
09.11.2012 LNG Terminal construction - over 1,7 million man-hours without a single serious accident
The Swinoujscie LNG Terminal construction team has worked over 1,7 million man-hours without a serious accident or a fatal accident. According to the EPC Contractor (Saipem - Techint - PBG consortium), only seven minor accidents...[more]